The Work Plan of the IHSM
Ref. nr/ |
Activities Title |
Responsible person |
Terms of implementation |
WPl. Strengthening professional competencies of CA teachers |
|||
1.1 |
Development of the ISM internal project plan |
K.O. Dzhusupov |
01.04.21 |
1.2 |
Needs assessment of ISM teachers’ needs |
O.G. Denisova, A.E. Bazhanova |
01.05.21 |
1.3 |
Intensive English language course (EEC) for 15-20 teachers |
A.E. Bazhanova |
24/07/21 |
1.4 |
Participation in training of trainers workshops at UMIL and UT |
K.O. Dzhusupov |
June-August 2021 |
1.5 |
Preparation and organisation of the Summer school on teaching methods and QA in EH , OH and PH |
B.N. Imankulova A.E. Bazhanova |
25/06/22 |
1.6 |
Purchase and installation of equipment |
K.O. Dzhusupov U.R. Musabaev |
15/06/21 |
WP2. MSc Modules Public Health |
|||
2.1 |
Updating& tuning existing PhD program in Public Health |
Dr. Asel Usenova |
01/02/2022 |
2.2
|
Development, peer-review and institutional adoption of shared and locally tailored modules of MSc modules with relevant learning outcomes, and educational materials adopted to b-leaming: |
|
|
2.2.1 |
- In the field of Environmental Health |
E.E. Ten |
|
2.2.2 |
- In the field of One Health & Epidemiology ofinfectious diseases |
A.A. Kamchybekova |
|
2.2.3 |
- In the field of Occupational Health |
Ch.T. Sulaimanova |
|
2.2.4 |
- In the field of Public Health |
K.O. Dzhusupov |
|
2.3 |
Development of the Practical Guide for Supervising MSc students |
K.O. Dzhusupov |
01/04/22
|
WP3. Quality Assurance System for Project Developments |
|||
3.1
|
3.1.3 Development of QA system for the project: QA indicators, questionnaires, reporting forms |
O.G. Denisova A.E. Bazhanova
|
01/05/2021
|
3.1.2. Preparing the procedure of ISM QC self- evaluation
|
O.G. Denisova
|
20/04/2021
|
|
3,1.3. Developing draft recommendations on peer evaluation of new MSc curricula/modules/courses
|
A.E. Bazhanova
|
|
|
3.1.4 Reports on peer-evaluation MSc modules/ courses. |
A.E. Bazhanova |
01/05/2020 |
|
3.1.5. Monitoring QA of the project: collecting data |
O.G. Denisova |
Every 6 month |
|
3.1.6. Open a call for external QA expert and |
A.E. Bazhanova |
01/04/2021 |
|
WP4. Launch of MSc modules |
|||
4.1 |
Recruiting MSc students |
A.E. Bazhanova |
01/09/2022 |
4.2 |
Launch & Delivery of graduate programs |
A.A. Usenova |
15/09/2022 |
4.3 |
Delivery b-learning |
U.R. Musabaev |
01/09/2022 |
4.4 |
Organisation of mobility of MSc students |
A.E. Bazhanova |
01/12/2023 |
WP5. Dissemination of the project results |
|||
5.1 |
a) Development of the ISM’s plan for dissemination, |
B.N. Imankulova
|
01/05/2021
|
5.2 |
Dissemination activities; preparing & posting news for the ISM ’s website and mass-media |
B.N. Imankulova U.R. Musabaev
|
All project life time
|
5.3 |
Preparing and publishing brochures/leaflets of the project Outputs
|
B.N. Imankulova O.G. Denisova
|
All project life time
|
5.4 |
Organising workshops at the national level with the participation of international experts |
A.A. Usenova, K.O. Dzhusupov |
01/11/2022 |
5.5 |
Organising and conducting of the International conference |
All members |
01/10/2023 |
5.6 |
Development of an agreement on the continued cooperation of the project participants for the development of its results after the project |
A.A. Usenova, K.O. Dzhusupov |
01/10/2023 |
WP6. The Project management |
|||
6.1
|
6.1.1. Development of the ISM work plan and |
A.A. Usenova, K.O. Dzhusupov |
01/05/2021 |
6.1.2. Organizing documentation of the events and activities of the project with keeping record by the local coordinator |
K.O. Dzhusupov
|
All project life time
|
|
6.2-6.3
|
Preparation of regular, mid-term and final reports.
|
K.O. Dzhusupov,
|
Regular reports on 6 |
6.4 |
Financial provision of the project |
M.I. Mayrikova |
All project life |
Work plan of the IHSM
The IHSM's Quality Assurance plan